February Bulletin
This month, concrete pours will pick up steam as we work our way out of the hole. Expect dirt and concrete trucks entering and exiting...
Concrete Pour on Dec 10th - Expect noise and heavy truck traffic
Monday 12/10, We will pour our fourth PT deck! TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and...
Concrete Pour on Nov 12th - Expect noise and heavy truck traffic
Monday 11/12, We will pour our third PT deck! TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and...
Concrete Pour on Oct 22nd - Expect noise and heavy truck traffic
Monday 10/22, We will pour our Second PT deck! TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and...
Winter is Here!
A snap from top of our tower crane as we mark the end of summer! Back-fill on the west side is currently scheduled for 10/8. The Telebelt...
Construction Update!
Below is the snapshot of shotcrete being carried out on the West side as per our update from last week. Framing hold downs and plumbing...
Construction Update
As of Friday (9/14), we have completed the concrete pour for West P1 PT deck! Typical traffic control measures across 165th were as seen...
Concrete Pour on Sep 14th - Expect noise and heavy truck traffic
Friday 10/14, We will pour our first PT deck! TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and...
Construction Update!
As of Wednesday (9/6/18), we are getting ready for P1-West PT deck concrete pouring scheduled for Thursday (9/13) and have already...
Construction Update!
As of Friday (8/24/18), we have poured the first lift of concrete for East Post-Tension concrete slab! Below is the snapshot of cables...